Guides / How to estimate a concrete order
PROJECT GUIDE

How to estimate a concrete order

From measured volume to a supplier-ready estimate.

Measure each pour

Separate the slab, thickened edges, steps and columns. Use the approved thickness and account for uneven ground; avoid counting overlapping regions twice.

Calculate volume

Multiply area by thickness in compatible units. A 12 × 10 ft slab at 4 in is 40 ft³, or 1.481 yd³. A 10% example allowance gives 44 ft³, or 1.630 yd³.

Compare supply options

At 0.60 ft³ per bag, 44 ft³ requires 74 bags. For ready-mix, use the order volume and ask about delivery, minimum loads and fees. Enter actual quotes, not the example prices.

Prepare the list

Transfer the already adjusted volume to the bag calculator or the comparison tool. The transferred allowance is zero to avoid adding it twice. Keep just the selected supply option on your shopping list.

Try these calculators